Mt Arthur Coal Mine
Lifetime emissions
193 million tonnes
Coal produced
67 million tonnes
Lifetime
4 years
| Lifetime emissions direct | 2.64 million tonnes |
|---|---|
| Lifetime emissions scope 3 | 190.20 million tonnes |
| Annual emissions direct | 0.66 million tonnes |
| Annual emissions scope 3 | 47.55 million tonnes |
| Annual emissions total | 48.21 million tonnes |
| Annual coal production | 16.75 million tonnes |
| Project timeline | 2027–2031 |
Federal approval process
Stage 3/6
State approval process
Stage 6/9